St. John's College Home Page Conference Services at St. John's College
  Summer 2011 | Virtual Tour | Facilities | Accommodations | Catering | Directions | Map | Contact Us
 

Construction and Renovation Updates
February 19, 2010

The Betty and Norman Levan Hall

The college has installed a web cam that updates every 60 seconds. Click here to view! 

The recent snow has not slowed progress on Levan Hall and we are still looking to a Fall 2010 opening!

The wood framing and decking for the west roof is virtually complete.  Early in the week of the 22nd, the roof will be covered by substrait (insulation and a lightweight concrete), then a synthetic membrane that is glued down. 

Interior work with plumbing, electrical, sprinklers, and HVAC work is still taking place inside the building, with about 25-30 workers indoors.  Towards the end of next week, insulation and dry wall will be going up within the building, starting on the lower level and moving up.  The polishing of the exposed concrete floors is almost done.

The Corten panels (steel panels that self-rust to a nice, permanent finish) for the vestibule are almost all up, as are those for the “bump out” area of the southwest seminar room on the top floor.  The sheathing of the west side of the building with “green glass” sheathing and work on the flashing is almost complete.

Coming up in the next week or so, we’ll see work on the window frames, as well as rough-grading for the handicap access path that will lead from Weigle to Levan, then to the first level entrance of Peterson.  We don’t anticipate hitting rock during this grading, however it’s a possibility, in which case rock cutting can be quite noisy and jarring. 

The east Peterson balcony will remain closed for a few more months due to some re-design work for stability.  It will be open by graduation! 

Behind Weigle, the ground is frozen, so the grading and paving will be delayed until March.   

The one-day electrical shut off for FAB and the Library has been moved to Tuesday, March 23. 


CMUs give Levan height

Architect’s rendering of the completed Betty and Norman Levan Hall
 

Removal of bridge between FAB and PSC

Debris Bins for LEED
 
     

Levan Hall f loor plans (Adobe PDF documents):

Lower level
Main level
Top floor

Click here for past construction updates

Coming Soon. . . The college plans to begin excavating for a new dorm project near the lower dorm area in June 2011.  Details to come!

Lower Dorm Courtyard Renovation

Phase One of this project is complete!  Photos to come.

Fine Arts Building Classroom Renovation

FAB 104 renovations are complete.  See the below photos. 


Completed


Work in Progress
 

Library Re-Carpeting

The library re-carpeting is complete for now. The music room will be completed in the fall. 

 

 

 


Summer 2011| Virtual Tour | Facilities | Accommodations | Catering | Directions | Map | Contact Us