Construction and Renovation Updates
Updated: December 5, 2011
Winiarski Student Center
Web Cam
This new residential center is moving along wonderfully, and is on schedule to open June 1, 2012!
At this time, crews are working both inside and outside the buildings. On the inside, all of the rooms are framed with some drywall and insulation in place. Crews are also putting in sprinkler system piping in the seminar rooms. Outside, crews are securing insulation around the buildings, in preparation for stucco work. Some of the smaller windows have been installed, and the glass for others is on-site. There are going to be some spectacular views from large windows, as well as some of the balconies (see photo below)!
The buildings are expected to be closed up for more dedicated interior work in December.
The basic structures for two of the three walking bridges (see photo below) have been completed and will eventually be covered with concrete. The two western bridges run from the gathering placita to buildings A and B. The third bridge, to building C, is in progress.
The interior floors of the dorms will primarily be polished concrete, with tile in the bathrooms. Radiant heating will be in the halls, bathrooms, common areas, and break rooms, while the individual dorm rooms will have their own heating unit and thermostat. The dorm bathrooms will have two showers, three sinks, two toilets, and “cubby” shelving with baskets for storing toiletries.
Carpet will be placed in tutor offices in the seminar building, and the seminar rooms will have cork floors. The seminar building will have some air conditioned spaces, as well as a fireplace in the meeting room, which is located on the top floor and will open onto the gathering placita.
This LEED Silver residential center is made possible by Warren and Barbara Winiarski and other friends of St. John's College. Rooms are slated to be open for use in summer 2012.
Gates to the site open at 8:00a. Note that large vehicles will be entering and exiting campus from Camino Cruz Blanca, using the main entry road, and the road to Lowers.

Bridge from Seminar Bldg to A
|

Western view from Seminar Building
|

Smoothing the concrete floors
|

From the south, second stories
|

View from West End
|
Crane in Action
|
Aerial View of Staging Area
Upper Floor Plan
Lower Floor Plan
Seminar Building Lower Floor Plan
Seminar Building Upper Floor Plan
Site Plan
The Betty and Norman Levan Hall
UPDATE: Levan Hall has reached LEED Gold certification! Congratulations to all who were involved with the careful planning and implementation necessary to create such a note-worthy “Green” building.
Levan Hall, home of the St. John’s College Graduate Institute is complete. Staff and tutors are moved in and classes are taking place.
Below are current pictures of the building.

Seminar Room 303 with balcony
|

Levan from the Pond Placita
|
|

The Darkey Graduate Common Room
|

East Balcony
|
|
Levan Hall floor plans (Adobe PDF documents):
Lower level
Main level
Top floor
Irrigation Work
Near the entrance to campus, new irrigation pipes have been installed to service the plantings along the road and sidewalk leading to the SAC driveway. A new automatic watering system is in use on the soccer field, and is working well.
Photos of Summer 2006 Hardscape Renovation and Fishpond Repair:
 |
 |
 |
| Fishpond Placita Facing the Bookstore |
Upper Placita Outside ESL |
Placitas and Pond with Working Waterfall |
Click here for past construction updates.
|